ANKARA–POZANTI HIGHWAY KEMERHISAR – EMINLIK SECTION CONSTRUCTION

Administration Name : General Directorate of Highways
Location : En Nigde
Date of Contract : 09.10.1998
Completion Date : 31.12.2010
Project Details : 55 km 2x3 Lane Motorway Construction 538 m viaduct, h= 44 m

DOLMABAHÇE-DOLAPDERE-PIYALEPAŞA-KAGITHANE TUNNELS

Administration Name : Istanbul Metropolitan Municipality
Location : İstanbul
Date of Contract : 10.08.2009
Completion Date : 27.04.2010
Project Details : 7.920 m tunnel with 6 m diameter

KAGITHANE- PIYALEPAŞA—BOMONTI -DOLMABAHÇE HIGHWAY TUNNEL & ELECTROMECHANICS CONSTURUCTION COMPLETION WORKS

Administration Name : Istanbul Metropolitan Municipality
Location : İstanbul
Date of Contract : 14.05.2007
Completion Date : 25.10.2008
Project Details : 7.920m Tunnel Construction & Electromechanics

INTERSECTION BRIDGES AT KAGITHANE TUNNEL PORTAL

Administration Name : Istanbul Metropolitan Municipality
Location : İstanbul
Date of Contract : 20.03.2008
Completion Date : 02.05.2009
Project Details : Bridge Interchange Construction

HATAP DAM CONSTRUCTION

Administration Name : General Directorate Of State Hydraulic Works 5th Regional Dir. ANKARA
Location : Çorum
Date of Contract : 27.01.1995
Completion Date : 21.04.2009
Project Details : .100.000 m2 Filling of main dam 650.000 m³ ,excavation 400 m diversion tunnel

DOLMABAHÇE-DOLAPDERE-PIYALEPAŞA-KAGITHANE TUNNELS

Administration Name : Istanbul Metropolitan Municipality
Location : İstanbul
Date of Contract : 10.03.2006
Completion Date : 24.08.2007
Project Details : 7.920 m tunnel with 6 m diameter

ANTALYA AIRPORT

Administration Name : General Directorate of State Airports Authority
Location : Antalya
Date of Contract : 30.06.1998
Completion Date : 19.04.2005
Project Details : 920.000 m2 Concrete Pavement, 40 cm thick 127.000 m2 Concrete Pavement, 30 cm thick

MILAS-BODRUM AIRPORT PAT FIELD CONSTRUCTION REPAIR

Administration Name : General Directorate Of State Airports Authority
Location : Bodrum
Date of Contract : 11.10.2016
Completion Date : 30.07.2019
Project Details : : 14.650 m Drainage Piping 600.000 m³ Excavation 435.000 m2 Jeogrid 355.000 m2 Laying of high quality coating concrete, 40 cm thick 437.000 m2 Laying of weak coating concrete, 15 cm thick

AMASYA HIGHWAY CONSTRUCTION

Administration Name : General Directorate of Highways - Regional Directorate of Samsun
Location : Amasya-Turkey
Date of Contract : 27.06.2016
Completion Date : 31.12.2020
Project Details : 3.300.000 m3 Earthworks 100.000 m3 Concrete works 80.000 m3 Stone fill 110.000 tons plant mix subbase 140.000 tons plant mix base 140.000 tons hot bituminous mixture

ESENBOGA AIRPORT PAT FIELD CONSTRUCTION, REPAIR AND EXTENSION INCLUDING DE-ICING APRON CONSTRUCTION

Administration Name : General Directorate General of State Airports Authority
Location : Ankara
Date of Contract : 25.03.2016
Completion Date : 28.10.2020
Project Details : Excavation: 1.800.000 m3 Filling: 1.200.000 m3 Concrete Works: 102.500 m2 Asphalt Works: 350.000 Tons Underpass Construction (10x30) 350 m

KADIKOY KURBAGLI STREAM IMPROVEMENT

Administration Name : General Directorate of Istanbul Water and Sewerage Administration
Location : Istanbul-Turkey
Date of Contract : 31.03.2016
Completion Date : 16.09.2018
Project Details : : 320.000 m3 Earthworks , 4.800m Concrete Pipe 34.000 m Piling, 4 Pre-Tensioning Bridge Construction 35.000 m3 Concrete Works, 8.400 Ton Steel Work

FULYA LEVAZIM HIGHWAY TUNNEL CONSTRUCTION

Administration Name : Istanbul Metropolitan Municipality
Location : İstanbul
Date of Contract : 24.03.2008
Completion Date : 02.05.2018
Project Details : : 4.070 m Tunnel Construction and Elektromechanical Works